The Client
Sheffmed Ltd are a global company who design and manufacture a range of specialist medical instruments. Their extensive selection of products comprises of instruments for ENT/Audiology, surgical LED headlights and a new generation of advanced laryngectomy equipment.
Sheffmed are based in South Yorkshire and are champions of pioneering British designs. They are also active in supporting healthcare initiatives in developing countries, including providing ENT equipment and funding building projects in Malawi as part of their contribution to global well-being.
The Challenge
With business booming, Sheffmed decided 2023 was the year for new premises that would allow them to streamline their operations. They secured a new building ready for a move in January 2024 and when it came to a mezzanine supplier, Hi-Level were the obvious choice having installed a mezzanine in their previous building.
With the new building secured and Sheffmed planning an ambitious weekend move for the new year it was Hi-Level’s role to ensure the mezzanine was installed on time and as planned to allow for minimum possible downtime in Sheffmed’s operational hours.
The Criteria
Sheffmed’s primary objective for their new site was to bring a large quantity of palletised stock that was currently being held in offsite storage under the same roof as their pick, pack and dispatch operation.
The mezzanine was to be used for storage of palletised stock and the area under the mezzanine would accommodate the pick, pack and dispatch process.
Specifications
- Single tier.
- Over 125m2 mezzanine floor.
- General access staircase with landing.
- Edge protection, swing pallet gate and load plate.
- One hour fire protection system including ceiling tiles, column casings and fascia.
The Result
The new mezzanine has provided Sheffmed with all the space they need for their growing business. Being able to hold all their stock on one site has not only reduced the costs associated with offsite storage and transport back to their warehouse but also streamlined their operation with additional stock being on hand as needed.
The new mezzanine floor has helped to future-proofed their business with Sheffmed hoping to be in their new building for many years to come.
Testimonial
“The process with Clyde, our Project Manager, was great – he was quick to respond to any queries we had and very informative.
I was shocked how quickly the mezzanine installation was completed! The installation teams for both the mezzanine and the fire protection were fantastic. We are very pleased with the overall product and high quality service Hi-Level have provided us.”
Joel Hutkai, Warehouse Manager at Sheffmed Ltd